Meridian buys 11.3% stake in Southland “AI factory” maker Datagrid for $54m

Meridian buys 11.3% stake in Southland “AI factory” maker Datagrid for $54m
Updated

Meridian buys 11.3% stake in Southland “AI factory” maker Datagrid for $54m

Chris Keall

Technology Editor/Senior Business Writer·NZ Herald·
25 Nov, 2026 10:26 PM5 mins to read
‌

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.Subscribe now

Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

Share

    Share this article

  • Copy Link
  • Email
  • Facebook
  • Twitter/X
  • LinkedIn
  • Reddit
A render of Datagrid’s Southland data centre, and (inset) founder and executive chairman Remi Galasso.

A render of Datagrid’s Southland data centre, and (inset) founder and executive chairman Remi Galasso.

Meridian Energy has paid US$30 million ($54m) for an 11.3% stake in Datagrid Holdings, the firm that plans to build a giant data centre in Southland.

The deal implies a $478m valuation for Datagrid.

Datagrid has also signed an option to buy 140 megawatts (MW) of power capacity from Meridian.
The option agreement is conditional on approval from the Electricity Authority.

 Meridian chief executive Mike Roan (left) with Datagrid founder Remi Galasso.
Meridian chief executive Mike Roan (left) with Datagrid founder Remi Galasso.

“We’ve currently got that [140MW] within our generation capacity, but we also have new generation that we’re building now and over the coming years,” Meridian said.

“For instance, next year we’ll open the Ruakākā Solar Farm, which is 130MW, and we have enabling works underway on two wind farms in the North Island, Mt Munro (90MW) and Te Rere Hau (172MW).”

Transpower said this morning that it was investigating the next phase of possible major investments in the lower South Island’s electricity transmission grid.

Consultation will run until February 5. The national grid operator is assessing more than 30 possible upgrade options through to 2040, which could cost anywhere from $718m (if existing assets are upgraded) to more than $6.9 billion with new assets.

Second backer

Meridian is the second gentailer to buy a slice of the Singapore-based Datagrid Holdings, headed by Remi Galasso.

In July, Mercury paid US$30m (at the time, $53m) for a 12.7% stake.

Datagrid also took a 140MW power purchase option with Mercury.

Mercury said the capacity could be supplied by renewable power projects under construction.

HEB has begun earthworks and construction at Datagrid's Southland "AI factory". Datagrid founder Remi Galasso says this initial "horizontal construction" was funded by Mercury's injection of capital in July. Photo / Datagrid
HEB has begun earthworks and construction at Datagrid’s Southland “AI factory”. Datagrid founder Remi Galasso says this initial “horizontal construction” was funded by Mercury’s injection of capital in July. Photo / Datagrid

In July, Galasso told the Herald that the Mercury money would be used for initial “horizontal construction” while he continued to pursue funds for the main build. Earthworks and work on a side road began in August.

Datagrid has not recently put a fundraising target on its Southland build, but Contact Energy has described a similar-sized facility – the 250MW data centre it wants to build in Taranaki in partnership with CDC – as a $4 billion project.

Microsoft spent north of $1b on its first data centre at Westgate, a sub-100MW facility.

And Spark sought to raise more than $1b for its data centre expansion, which centred on a proposed “surf park” data centre at Dairy Flat north of Auckland, the centrepiece of an expansion to more than 90MW capacity.

It ultimately raised the funds by selling 75% of its data centre business to Australia’s Private Equity Partners, but the surf park build is currently stalled.

Creating jobs

Meridian chief executive Mike Roan said it was committed to supporting the country’s long-term prosperity and energy security.

“New Zealand already operates one of the most renewable electricity systems in the world, providing a strong foundation from which to grow and electrify more of our economy.

“Datagrid could be the first of many new and varied businesses that we can attract to our shores to create jobs and grow regional economies in a low-emissions manner.”

Galasso told the Herald that Datagrid would create “200 to 300″ ongoing jobs, based on staffing at similar facilities overseas, which he describes as “one employee per megawatt” as a rule of thumb.

Microsoft said earlier this week that its new data centre at Westgate would create 40 ongoing jobs (and 500 at peak consumption).

The tech giant didn’t give a power capacity for its latest build, but its backup provisions indicate it will be a facility up to 38MW.

Downsized ambitions

An early Datagrid promotional video promoted a US$5b data centre.

A 78,000sq m hyperscale facility would be scaled up to 1GW (1000MW) capacity (data centres are described by their peak power consumption).

More recently, as it signed an agreement with Transpower for a new substation (which Datagrid will pay for), the start-up has called its data centre a 280MW data centre. That would still be the largest in New Zealand (for context, a recent Fitch survey said the 60 data centres in New Zealand today have a combined 170MW capacity).

The 280MW figure still features on Datagrid’s website, but a press release from the firm this morning, and a Meridian NZX filing, use a 300MW figure.

Datagrid's Tasman Ring will now start with a downsized "Phase One" design. So far, only a marine survey, not the cable itself, has been funded.
Datagrid’s Tasman Ring will now start with a downsized “Phase One” design. So far, only a marine survey, not the cable itself, has been funded.

Datagrid has also downsized its ambitions for an international fibre optic cable to export its “compute” power to the world, after the withdrawal of initial partner Chorus from the project.

It is now trying to raise funding for an Invercargill-to-Melbourne cable.

Its initial “Tasman Ring” plan was for a loop linking multiple New Zealand and Australian centres, including Hobart, Sydney, Auckland and Taranaki. Galasso still hopes to fund a full version of the cable.

The proposed Tasman Ring Network would allow Datagrid to export its AI processing capacity. Image / Datagrid
The proposed Tasman Ring Network would allow Datagrid to export its AI processing capacity. Image / Datagrid

He said in July that he could not comment on how much capital Datagrid was seeking in total, but that “the overall project funding will be structured primarily around credit finance”.

Debt has emerged as the primary mechanism for funding new data centre builds in the US and around the world.

For example, in its recent investor update, Infratil said CDC’s net debt increased from A$5.98b on June 30 to A$7.14b as of September 30. (Infratil owns just under half of CDC, which operates data centres on both sides of the Tasman.)

Microsoft 6399 New Zealand owed its corporate parent at least $550m after building its first data centre at Westgate.

It’s anticipated that total borrowing to build and kit out data centres in the US will reach US$750b this year and US$1 trillion next year.

There is one major data centre under construction in NZ at the moment: Microsoft’s second facility at Westgate in northwest Auckland.

CDC and Contact Energy have applied for resource consent to build a 250MW data centre in Taranaki, which Contact has described as a $4b project.

Chris Keall is an Auckland-based member of the Herald’s business team. He joined the Herald in 2018 and is the technology editor and a senior business writer.